Great Lakes Dock and Dredge Company


This slideshow will introduce you to the company that will construct the nourished beaches in Kill Devil Hills, Duck, Southern Shores and Kitty Hawk during the summer of 2017.  You can print a PDF of this slideshow by clicking on this link:
Great Lakes Dredge & Dock Presentation 

January 20, 2017
Updated Beach Nourishment Project Schedule and Q & A Meeting

The contractor for the Town of Kill Devil Hills Beach Nourishment Project, and for the Towns of Duck and Kitty Hawk projects, Great Lakes Dredge and Dock (GLDD), has provided an updated projected schedule for the beach nourishment work.  The project dates for KDH have been moved forward and construction is now projected to begin in early August and conclude in early to mid-September, a potential overall time reduction of as much as 15 days.  Nourishment mobilization operations, including laying subline and assembling land based machinery, will begin approximately one month prior to construction to be ready once the construction dredge is on site. 

Projected Bid

Package Schedule

Projected January
2017 Schedule

Start Date

End Date

Duration

Start Date

End Date

Duration

Town of Duck

April 1

June 1

60 days

Mid to Late May

Mid to Late July

60 days

Town of Kitty Hawk

June 1

August 20

80 days

Mid-June

Mid-August

60 days

Town of Kill Devil Hills

August 20

October 10

50 days

Early August

Early to Mid Sept

35-45 days


Please remember:
  The beach nourishment start dates are subject to change.     

This information is not binding and is meant to provide estimated beach nourishment construction times for planning purposes.  Dates for the project can be affected by weather conditions, equipment demands, etc. 

Great Lakes Dock and Dredge Company selected for the overall Dare County/Kill Devil Hills/Duck/Kitty Hawk beach nourishment project.