Create an Account - Increase your productivity, customize your experience, and engage in information you care about.
View the Town’s Shoreline Protection Project Maintenance Plan
For a downloadable, printable version: Beach Nourishment Update
Ken Willson, part of the engineering team overseeing the Town of Kill Devil Hills’ beach nourishment project, is a contributing author to an article:
"Beach nourishment profile equilibration: What to expect after sand is placed on a beach."
The article states, in part, that "The objective of this paper is to explain the process of profile equilibration in a non-technical way to inform coastal communities and increase public understanding of how beach nourishment works.”
Once a beach nourishment project has been completed, the beach profile will adjust over time. This adjustment process is called “profile equilibration” and typically occurs within 12 months following sand placement, depending on various conditions.
This article states “…profile equilibration…dramatically decreases the width of dry beach from the very wide beach observed immediately after nourishment. This decrease in beach width (profile equilibration) is often misunderstood by some of the public as the failure of the beach nourishment project because they perceive “all the sand washed away.”
"... Beach nourishment projects are designed to take advantage of the natural process by including a volume of sand intended to be transported offshore."
Special thanks to Mr. Willson and the other contributing authors of this article: Gordon Thomson, Tiffany Rosters Briggs, Nicole Elko, and Jon Miller.
"Beach nourishment profile equilibration: What to expect after sand is placed on a beach."
Check out the Beach Nourishment Update below and also check out the latest More Beach to Love Video Update: July 28, 2017 Update
|
Previously Projected May 2017 |
New June/July 2017 Schedule |
||||
|
||||||
Start Date |
End Date |
Duration |
Start Date |
End Date |
Duration |
|
Town of Kill Devil Hills |
Early August |
Mid September |
40 |
Late June |
Mid August |
40 days |
There has been a major change in the beach nourishment schedule for the Town of Kill Devil Hills’ project. Great Lakes Dock and Dredge (GLDD), the beach nourishment contractor, will begin nourishment dredging in Kill Devil Hills in late June or early July. Completion of the Kill Devil Hills project is now anticipated to be in mid-August.
The overall nourishment project began in Duck in May, and GLDD has been operating three dredges to pump sand onto the beaches. Originally, two of the three were to be relocated to another area away from the outer Banks during the month of June. GLDD now anticipates that the Dodge and Padre Island Dredges will be available to stay on the Outer Banks until early to mid-July. In order to maximize the production of these to dredges, they will construct the portion of the project closest to the offshore borrow area, which is Kill Devil Hills.
The bid package for the overall beach nourishment project, Duck/Southern Shores/Kitty Hawk/Kill Devil Hills, did not specific the order in which construction would proceed to allow Dare County the ability to maximize cost savings that could be achieved through scheduling flexibility.
GLDD will begin mobilizing in Kill Devil Hills immediately to prepare for dredging anticipated to begin in the coming weeks. The company intends on landing a subline, which is a large steel pipe that leads out to the dredge from onshore, in Kill Devil Hills sometime early next week. The Helga Street beach access remains GLDD’s staging site for the Kill Devil Hills’ project.
The Town of Kill Devil Hills will continue to provide up-to-date nourishment project reports on this website and through www.morebeachtolove.com.
This article on how a beach profile is adjusted overtime once a beach nourishment project is completed. Kenneth Willson, one of the paper’s contributing authors, is part of the project’s engineering team overseeing the Town of Kill Devil Hills’ beach nourishment project.
The adjustment process is called “profile equilibration” and typically occurs within 12 months following sand placement, depending on various conditions. The article states “…profile equilibration…dramatically decreases the width of dry beach from the very wide beach observed immediately after nourishment. This decrease in beach width (profile equilibration) is often misunderstood by some of the public as the failure of the beach nourishment project because they perceive “all the sand washed away.” The objective of this paper is to explain the process of profile equilibration in a non-technical way to inform coastal communities and increase public understanding of how beach nourishment works.”
We hope you find it to be of interest and value.
With the upcoming beach nourishment project, you may have questions about what is expected to occur, what the nourishment timelines are, and if it may affect you. Check out the information on this page and the others listed to the left of this column. We believe you'll find the information helpful.
Dare County has developed an excellent resource at its "More Beach To Love" site, which provides information on all nourishment projects in Dare County, that will include an interactive map when the project begins.
The Town of Kill Devil Hills staging area is located on the upland portion of the beach lot located at Helga Street. The contractor will attempt to minimize the area utilized within the staging area as best as practical as the beach and adjacent areas are used heavily by the public throughout the year. The contractor will cordon off and/or fence the access and staging areas to prohibit public access. Outside of emergency vehicle access, the staging areas and construction accesses do not need to remain open to the public while the areas are in use for the Project. It is anticipated that the contractor would attempt to minimize needless closure of the public access if the contractor is not actively using the access. All access and staging areas shall be restored to the pre-construction condition upon project completion at the cost of the contractor.
Town ClerkP.O. Box 1719Kill Devil Hills, NC 27949